•Workshop PEB shed: 7514 sqm. •Piling: 1387 nos. of 750 mm dia & 25 m avg. depth.
Construction of 1.7 km Priority Section of Nagpur Metro
Construction of 1.7 km Priority Section Ch: KM 19.550 to KM 296 including 1 no. At-grade
and 1 no. Elevated Metro Station of Nagpur Metro
Nagpur Metro
Key Activities
•Earthwork in formation filling: 60000.00 cum •Retaining wall: 2.5 km •Minor Bridge: 2 Nos. •Metro stations: 2 nos. (1 at-grade & 1 elevated)
Design and Construction of Elevated Metro Viaduct and Platform Girders for Reach-2A, Nagpur Metro Rail Project, Phase-II
Design and Construction of Elevated Metro Viaduct of length 6.92 km from Ch: 657.182 M
to Ch: 7576.78 M including casting and launching of Platform Girders for 6 elevated Metro
Stations in Reach-2A, Nagpur Metro Rail Project, Phase-II
Nagpur Metro
Workshop shed at Sultanpur Metro Depot, DMRC, Delhi
Delhi Metro Rail Corporation(DMRC)
Holistic Techno Engineers
A-57, 3rd Floor, Block A, Sector 4, Noida
Our Mail
info@holistictechno.in
The idea of Holistic Technoengineers embodies the perspective that engineers must consider the entire system and the full scope of work for a project’s success. This new breed of Holistic engineers will not only be comprehensive problem solvers but also problem definers, leading multidisciplinary teams, setting agendas, and fostering innovation in construction and infrastructure development.